|
TOWN
WHARF ENVIRONMENTAL IMPROVEMENT /
MAINTENANCE SCHEME (Updated 16th July 2002)
The
Town Wharf Environmental Improvement Scheme Phase One works are
located next to the River Wey in the centre of Guildford and include
repaving the area with 450 x 450mm slabs and granite cubes, construction
of a flight of 'sitting' steps and the installation of ducting and
architectural lighting, street furniture and the 'Bargeman' statue.
The cost of the scheme is �85,000 which includes very generous contributions
from the Guildford Society, Legal and General and National Trust.
The scheme is being jointly designed
and supervised between Engineering Services and Projects and Public
Realm. This page will focus on the construction of the csheme over
the next five to six weeks and subject to resources we hope to update
this page weekly with progress reports and photographs. After the
environmental improvement works are completed, part of the nearby
river bank is to be rebuilt as part of an on-going maintenance programme.
|
|
UPDATE
ONE � 27th MARCH 2002
Progress
Report: - Work has started on the scheme with site fencing, accommodation
and pedestrian routes set up. The area is being excavated and a small
retaining wall is being built to support the wide �sitting� steps
which are due to be constructed next week. |
 |
Photograph
one taken 27th March 2002 showing initial excavation
and start of retaining wall being built in the centre of the
photograph. |
|
|
UPDATE
TWO � 5TH APRIL 2002
Progress
Report: - Works on the �sitting� steps are progressing well and
are nearly complete pending the final �infill� paving being laid.
The previous paving has now been removed and excavated down to the
formation level. The outside extent of the works has now been saw
cut in readiness for further excavation next week.
|
 |
Photograph two taken 5th April, showing
the nearly completed �sitting� steps and area of excavation
and the �artist� designed planter to the right of the new steps. |
|
| |
|
UPDATE
THREE � 12TH APRIL 2002
Progress
Report: - The �sitting� steps are now complete with the final paving
infill now done. All the area, which is due to be re-paved, has
now been excavated down to formation level. Ducting for the new
lighting scheme is being installed and the foundation for the bargeman
statue has been cast with it�s fixings.
|
 |
Photograph three taken 11th April, showing the completed
�sitting� steps with infill paving and the foundation/ six fixings
for the Bargeman statue can be seen in the centre of the photograph. |
|
| |
|
UPDATE
FOUR � 19TH APRIL 2002
Progress
Report:- Paving slabs and granite setts have now been installed
around the crane building as can be seen in photograph four and
works have started on the main circular granite sett feature which
will eventually surround the bargeman statue, who is due to installed
next week.
|
 |
Photograph four taken 19th April showing the granite setts and slabs
around the crane building. |
 |
Photograph five
taken 19th April showing the construction of the
main circular feature in light and dark granite setts. |
|
| |
|
UPDATE
FIVE � 26TH APRIL 2002
Progress
Report: The Bargeman statue was delivered to site and erected on Wednesday
23rd as shown in photograph six. Progress also continued
with the paving slabs, granite setts and the stone coping along the
river bank was laid. Now the main circular feature is� nearly complete,
work has begun on the secondary smaller granite circle. |
 |
Photograph
six taken 24th April showing the bargeman sculpture
just after being fixed in position in centre of main circular
feature. |
 |
Photograph
seven taken 26th April showing the slabs now laid
at the river edge. The bargeman has been temporarily covered
over to protect it until the remaining works are complete.
|
|
| |
|
UPDATE
SIX � 3RD MAY 2002
Progress
Report: Work is continuing on the installation of the last area of
the granite setts and the task of pointing all the setts with a cement
mortar has now started. The artist designed seats as shown in photograph
eight below have now been delivered and were installed this week.
|
 |
Photograph
eight taken 3rd May showing the two newly installed
artist designed seats. |
|
| |
|
UPDATE SEVEN � 17TH
MAY 2002
Progress
Report: Work on phase one is now substantially complete and all the
setts and paving have been laid and the final pointing of the joints
is being completed. Now
that these works have been completed on target the river bank repairs
will start shortly by a specialist contractor and then our main contractor
will return to finish off the lighting and a small area of additional
paving. |
 |
Photograph
nine taken 17th May 2002 showing the extent of the
new works and the second circular feature.
|
|
| |
| If
you require any further information on the construction please contact
the Resident Engineer, Nevil
True in Engineering Services on 01483 444524. However if you require
If you require any general information on the scheme please contact
Kay Munt, Projects and
Public Realm on 01483 444668 or alternatively visit the special projects
webpage. If you have any general comments on the Engineering Services
website, or these updates please contact Steve
Elliott. |
| |
|
TOWN WHARF ENVIRONMENTAL IMPROVEMENT
- RIVER BANK MAINTENANCE WORKS
UPDATE EIGHT - 16TH JULY 2002
(MAINTENANCE WORKS)
Progress Report: As work on phase
one of the environmental improvement scheme is now nearly complete
with the bins, bollards and lighting installed, work has now started
on the maintenance works for the river bank to prevent further collapse.
The old partially collapsed wall was removed using a long-reach
excavator. A large tree stump was uncovered which proved difficult
to remove. The new steel sheet piles, 4.5m to 5.0m long had to be
driven into the river bed using an air hammer, leaving just 150mm
above the water level. The void behind the steel piles has been
filled with concrete ready for the new engineering brick wall to
be built. Once the wall has been built, the area behind it will
be backfilled and repaved to match the environmental improvement
scheme.
|
|
|
Photograph ten
taken 16th July showing steel piling and ducting for last uplighter. |
|
| As soon as these maintenance works
are finished then the final surfacing and final uplighter will be
installed and the works will be fully open to the public and their
will be one final update on this webpage showing the final works in
update no nine which is anticipated to be in late July / early August. |
| Works started: |
Late June 2002 |
| Anticipated works completed: |
Mid August 2002 |
| Detailed Design / Site Supervision: |
GBC Engineering Services |
| Contractor: |
Ringway / Junior Construction |
| Funding: |
Guildford Borough Council |
| Total Cost: |
�20,000 |
|
| |
|
FINAL UPDATE -SEPTEMBER 2002
Progress Report: All works are now
fully complete and the repair works and lighting have been installed.
Works has now started on the design for the phase two works to finish
off the scheme.
|
 |
Photograph eleven
showing uplighters and new columns |
|
|
Photograph twelve
showing close up of the lighted bargeman and gravel surround. |
|
| |
| If you require any further information
on the construction please contact the Resident Engineer, Nevil
True in Engineering Services on 01483 444524. However if you require
If you require any general information on the scheme please contact
Kay Munt, Projects and
Public Realm on 01483 444668 or alternatively visit the special projects
webpage. If you have any general comments on the Engineering Services
website, or these updates please contact Steve
Elliott. |
| |
| Works
started: �� |
25th
March 2002 |
| Anticipated
works completed:� |
May
2002 |
| GBC
Civil Engineers:� |
Nevil
True / Steve
Elliott |
| Lighting
Engineer:�� |
Muzzafar
Bhatti |
| Outline
Design / Client:� |
Project
and Public Realm � Kay
Munt |
| Detailed
Design / Site Supervision: |
GBC
Engineering Services |
| Contractor:� |
Ringway
/ Junior Construction |
| Funding: |
Guildford
Borough Council, Guildford Society, Legal and General & National
Trust |
| Total
Cost: |
�85,500 |
|
| |